Block making processing 制砖流程
- The wheel loader will take the aggregate such as gravel, sand etc., to be loaded into the batching hoppers
- The skip elevator with the correct mixed proportion of raw material is elevated to the position of mixer and material will be discharged into the mixer.
- Raw material is being discharged into the mixer water and cement will be added simultaneously before mixing process begin.
- After mixing, the mixed material will be transferred to the head position of block machine (base mix feeder) with this system.
- Freshly made block are being churned out from the block machine
- The pallet elevator is made of solid steel section. The lifting elements consist of steel chains with solid angles. These angles lift pallets. The elevator can be manufactured from 9-12 level whereby each level can fit 2 pallets.
- Finger car moves the fresh block into the curing chamber
- Fresh blocks will be loaded into the curing chamber for curing. And after 8 hours of curing, cured blocks are taken out from curing chamber by the finger car.
- The cured block is being un-stacked from the lowerator and is being transferred to cubing area.
- The un-stacked blocks transferred to the Block/Pallet Alignment Device, and it align 2 pallets of cured blocks in order to ease the cubing system.
- Cuber will clamp 2 pallets of blocks each cycle, and with free turning system of 360°, each level will cross stack on top of one another on the block exit conveyor. And then be transferred to outside of the workshop by the exit conveyor.
- When the pallets have been emptied, the pallets will be swept, cleaned and oiled with this system
- Empty pallets are overturned here to be return to the block making machine form another production cycle.